Project Timeline

The tentative timeline below gives Seneca Falls School District residents a measure to gauge the progression of the capital project that was approved by district voters on December 19, 2017.

This timeline will be updated as changes are made.  

Steps in Construction Project Anticipated Completion Date
PROPOSED PROJECT PRESENTED TO DISTRICT
RESIDENTS FOR APPROVAL
DEC. 19, 2017----COMPLETED
PRODUCTION OF CONSTRUCTION DOCUMENTS BY ARCHITECTS (1)  JAN. 2018 - MARCH 2019----COMPLETED
NYS EDUCATION DEPT. REVIEW & APPROVAL OF ALL DOCUMENTS APR. 2019 - OCTOBER 2019----COMPLETED
CONSTRUCTION BID OPENING DEC. 2019----COMPLETED
REFERENDUM TO INCREASE COST OF PROJECT FEB. 25, 2020----COMPLETED
CONSTRUCTION PERIOD  MAR./APR. 2020 - AUGUST 2021
COMPLETION OF CONSTRUCTION AND
CLOSEOUT   
SEPTEMBER 2021 - NOVEMBER 2021