Tentative Project Timeline


  • The tentative timeline below gives Seneca Falls School District residents a measure to gauge the progression of the capital project that was approved by district voters on December 19, 2017.

    This timeline will be updated as changes are made.  


    PROPOSED PROJECT PRESENTED TO DISTRICT
    RESIDENTS FOR APPROVAL                                              DEC. 19, 2017----COMPLETED

    PRODUCTION OF CONSTRUCTION
    DOCUMENTS BY ARCHITECTS (1)                                     JAN. 2018 - MARCH 2019----COMPLETED

    NYS EDUCATION DEPT. REVIEW & APPROVAL
    OF ALL DOCUMENTS                                                          APR. 2019 - OCTOBER 2019----COMPLETED

    CONSTRUCTION BID OPENING                                         DEC., 2019----COMPLETED

    REFERENDUM TO INCREASE COST OF PROJECT              FEB. 25, 2020----COMPLETED

    CONSTRUCTION PERIOD                                                   MAR./APR. 2020 - AUGUST 2021

    COMPLETION OF CONSTRUCTION AND
    CLOSEOUT                                                                           SEPTEMBER 2021 - NOVEMBER 2021